| Osceola High School Comprehensive Renovation, Project Schedule |
|
Phasing
Plan (Click for bigger) |
| Schedule Information |
| In
order to minimize any disruptions to students and staff during construction
this project has been split into three phases. Phase 1- September of 2009-December of 2010, In Red During this phase the new gymnasium/cafeteria and auditorium buildings will be constructed. In addition a new service building will be built which will provide air conditioning to the entire campus. Building 900, which houses the current auditorium, will be renovated. Phase 2- December of 2010 to May of 2012, In Green In this phase four new classroom buildings along with the new administration/guidance building will be constructed. In order to do this a few existing buildings will be demolished. Building 2900, which houses the life skills lab, will be renovated. The front parking lot will be redone. Phase 3- April of 2012 to August of 2012, In Blue During this phase all the portables added during the first two phases will be removed. The site work will be finished including the new courtyard in the center of campus. Improvements to the football stadium and its facilities will be made. Building 1100, which currently houses classrooms, will receive additions and renovations. Finally, the new student parking lot will be finished. |
|
|